Highway 12B construction delayed

May 07, 2018 - 09:00

Efforts to restore and upgrade National Highway 12B section in Nho Quan district and Tam Điệp city of Ninh Bình Province will likely not be completed by late June as scheduled due to lack of progress on ground clearance.

Efforts to restore and upgrade National Highway 12B section in Nho Quan district and Tam Điệp city of Ninh Bình Province will likely not be completed by late June as scheduled due to lack of progress on ground clearance. – Photo baoninhbinh.org.vn

NINH BÌNH – Efforts to restore and upgrade National Highway 12B section in Nho Quan district and Tam Điệp city of Ninh Bình Province will likely not be completed by late June as scheduled due to lack of progress on ground clearance.

Although the authorities of Nho Quan District and Tam Điệp City have carried out several ground clearance measures for the investors to accelerate the project’s progress, many spots have not yet been cleared, according to project’s representative.

At present, the road section through Tam Điệp City with total length of 4.7km, but 1km still requires clearance. The reason given for the delay was that the local people did not agree with compensation plan.

Meanwhile, the 28.750km-road section in Nho Quan District could not be constructed because of protests by 250 local households who refused the compensation money and allocation plan.

At present, the Ninh Bình People’s Committee has asked the provincial Transport Department and Natural Resources and Environment Department to push Nho Quan District authorities to solve the obstacles, the project’s representative told the paper.

The stagnancy of ground clearance would cause a slowdown in the project’s progress and render the June 30 completion date untenable, he said.

So far, the project has completed 9km of concrete road, 3km of asphalt road, the five bridges of Mí, Láo, Sui, Vĩnh Khương and Điếm Tổng and fixed girders of Rịa and Lập Cập bridges.

The road section of the Nho Quan –Tam Điệp National Highway 12B was designed for car speeds of 60-80km per hour with width of 7m. It is capitalized at VNĐ1.17 trillion (US$51.7 million) from Government bonds.

The section was an important road linking the National Highway 1 to Hồ Chí Minh Expressway, and served for rescuing activities when discharging flood of the Hồng (Red) River and fire in Cúc Phương National Park.

The National Highway 12B would help to develop the local economy and ensure national defence for the country’s northwestern region as well as reduce traffic congestion during festive seasons of Ninh Bình Province. — VNS

    

 

 

 