The city’s Urban Transport Infrastructure Projects Management Board on Wednesday explained fare hike suspicion of rapid bus purchase as reported by local media recently.

" />

BRT bus prices reported wrongly

March 10, 2017 - 09:00

The city’s Urban Transport Infrastructure Projects Management Board on Wednesday explained fare hike suspicion of rapid bus purchase as reported by local media recently.

A BRT bus on Hà Nội’s Giảng Võ Street. — VNA/VNS Photo Quang Quyết
Viet Nam News

HÀ NỘI — Authorities have ‘corrected’ several figures cited recent media reports on the purchase of buses to ply the capital city’s BRT (Bus Rapid Transport) routes.

The Management Board of the Urban Transport Infrastructure Projects Management Board provided the clarifications on Wednesday.

The reports had said that the bus purchase process went through two tenders within a month, and that the capital city’s Transport Department had approved results soon after, choosing Thiên Thành An Joint Stock Company and Trường Hải Auto Corporation (THACO) over Swedish Volvo.

The purchase contract was signed on December 09, 2015.

The reports had said that THACO had delivered 35 buses worth VNĐ194 billion (US$8.6 million), about VNĐ5.543 billion ($245,700) each to Hà Nội.

The price was said to be high, compared to what the most advanced, fully equipped 47-seat cars were selling in the Vietnamese market for at VNĐ4.2 billion ($186,700).

Phạm Hoàng Tuấn, director of Hà Nội’s Urban Transport Infrastructure Projects Management Board, said that the tendering process was announced internationally in 2014 following national and World Bank (WB) regulations.

The successful bidder was Openasia Equipment Limited, which offered the Volvo Bus for $11.6 million including costs for operation, training, technology transfer, taxes and vehicle checking fees.

However, the post-tender negotiations failed because the bidder did not accept several requirements and offered conditions that did not abide by bidding regulations. The city’s Transport Department then issued a decision in March 2015 to cancel the tender.

Following agreement from the WB, the second tender was opened and its result was approved by the city’s Transport Department. The bid was for VNĐ176.29 billion ($7.9 million), including above-mentioned costs, lower than the first tender by $3.7 million. The successful tender was submitted by the Thiên Thành An Joint Stock Company and THACO.

Tuấn said the media reports had wrongly reported the time taken between the two tenders as one month, when it was eight months.

As for prices under the second tender package, which media reports put at over $12.34 million, compared to $11.65 million in the first winning bid, Tuấn said that it was an estimated value, not the tender price. The value included domestic taxes, fees and contingency costs not included in the tender price.

The actual bus cost was VNĐ5.03 billion, including VNĐ4.91 billion ($218,200) for the bus and the remaining for other expenses, the board said.

The buses, which can hold up to 90 passengers, have special features that are different from normal buses, including higher floors and automatic door opening systems.

After obtaining agreement from the WB and approval from Hà Nội’s People’s Committee, a VNĐ17.7 billion ($786,600) package was added to the tender to install modern equipment that would synchronise BRT operations. The package has not been accounted for so far.

Tuấn said any project that uses the WB’s Official Development Assistance loans must not only follow Vietnamese laws but also adhere to international regulations. They are also subject to occasional supervision during the design, estimate and tender processes by the WB, he added.

The project has also been audited by State Audit Office of Việt Nam. The management board and the Transport Department are studying traffic flows to efficiently operate BRT following the project’s targets, Tuấn said.

The BRT project, financed with WB loans worth VNĐ1.1 trillion ($53.6 million) started its pilot phase on December 15 last year. The BRT route, covering 14.7 km, begins at the Kim Mã station in Ba Đình District and ends at the Yên Nghĩa station in Hà Đông District. — VNS

 

 

 