Nhổn-Hà Nội Railway Station Metro Line to be examined from September

February 05, 2020 - 00:20

The Hà Nội Metropolitan Railway Management Board is making plans to recruit and train workers for the line’s operation and maintenance.

 

Việt Nam will receive the first locomotive for dynamic tests in July. — VNA/VNS Photo

 

HÀ NỘI — A metro project connecting Nhổn area in Bắc Từ Liêm District and Hà Nội Railway Station is set to have initial dynamic tests from September.

The first locomotive of the 10 trains with a capacity of 950 passengers each manufactured in France by Alstom Company will be sent to Việt Nam in July for tests in September and trial runs in March 2021.

The Hà Nội Metropolitan Railway Management Board is making plans to recruit and train workers for the line’s operation and maintenance.

“Trains will run first on the elevated section spanning 8.5km connecting Nhổn area and Cầu Giấy District in April 2021,” the board announced.

The remaining 4km underground line is set to be finished in December 2022.

Hà Nội People’s Committee has adjusted the project’s execution time and investment structure.

The metro line was previously planned to be built from September 2010 to September 2017. With the adjustment, it will be implemented from 2009 to 2022 with trains launched in December 2022.

Of 1.17 billion euro invested into the project, Hà Nội has reduced a portion allocated from French Development Agency (AFD) from 178.7 million euro to 158.7 million euro and increased a loan from the French government from 335.4 million euro to 355.1 million euro.

The trains are expected to be operated at 35km per hour on average and 80km per hour maximum, the same speed as metros in Paris, Berlin and other cities in Asia.

The trains' colours – coral and yellow – are inspired by Việt Nam’s dragon fruit and paddy fields.

The metro line will run through districts of Bắc Từ Liêm, Nam Từ Liêm, Cầu Giấy, Ba Đình, Đống Đa and Hoàn Kiếm. — VNS

 

 

 

 