HCM City authorities have proposed increasing capitalisation for the city’s first two metro lines as the projects continue to face a capital shortage.  

" />

City seeks more funds for metro lines 1, 2

January 11, 2018 - 08:00

HCM City authorities have proposed increasing capitalisation for the city’s first two metro lines as the projects continue to face a capital shortage.  

An elevated section of HCM City’s Bến Thành – Suối Tiên metro line runs along Hà Nội Highway. VNS Photo Mạnh Linh
Viet Nam News

HCM CITY — HCM City authorities have proposed increasing capitalisation for the city’s first two metro lines as the projects continue to face a capital shortage.  

The city People’s Committee has sent a report to the Government on the details of cost overruns.

The metro line No 1 from Bến Thành in District 1 to Suối Tiên Theme Park in District 9 was approved by the city in April 2007 with an investment of VNĐ17.4 trillion (US$766.4 million). At that time, approval by the National Assembly (NA) was not needed.  

After investment costs were re-calculated by consulting agencies, costs increased to more than VNĐ47.300 trillion ($2.08 billion).

The city government attributed the surging costs to price changes of materials, minimum wage hikes in the 2006-2009 period, and the depreciation of the Vietnamese đồng and Japanese yen, among others.

The PM agreed with the city Government to approve the project adjustments in August 2011. With investments reaching more than VNĐ47.3 trillion, the NA then had to approve the amount.

As proposed by the city government, the PM assigns an agency to report to the NA on investment adjustments and assists the city in advancing capital to continue work on metro line No 1.

According to the city People’s Committee, the city has signed three loan agreements worth VNĐ31.208 trillion, of which VNĐ11.929 trillion has been disbursed.

The project has implemented four bidding packages and has completed around 48 per cent of the work.  

As for metro line No 2, which connects Bến Thành with Tham Lương in District 12, the city People’s Committee approved a design by a local consulting firm in 2010 with a total investment of $1.37 billion.

In 2012, the IC, a consortium from Germany chosen as the international consulting firm two years later, revised the detailed design of the project with a total investment of $2.1 billion.

In 2015, the city government petitioned the PM to adjust the investment cost of the metro line No 2 project. 

The city government has asked the PM to approve the project’s investment and implementation adjustments and allow the city to assess and approve project adjustments.

According to the Ministry of Transport, Ministry of Planning and Investment and the State Bank of Việt Nam, metro line No 2 can be approved by the city authority but comments from the PM are needed before implementation.

According to the Ministry of Construction and Ministry of Finance, the project needs to be reported to the PM before it is submitted to the NA for approval. — VNS