Việt Nam's National Power Transmission Corporation (EVNNPT) launched 36 power transmission projects with a total investment capital of VNĐ19.74 trillion (US$850 million) in 2019.

 

Workers of Việt Nam's National Power Transmission Corporation check equipment. The company launched 36 power transmission projects with total investment capital of VNĐ19.74 trillion (US$850 million) in 2019. VNA/VNS Photo 

HÀ NỘI — Việt Nam's National Power Transmission Corporation (EVNNPT) launched 36 power transmission projects with a total investment capital of VNĐ19.74 trillion (US$850 million) in 2019.

This marked the highest investment in the past three years and fulfilled 101.2 per cent of the work assigned by the State-owned Việt Nam Electricity (EVN) group.

Of the 36 projects launched, there were four 500kV power transmission projects and 32 220kV power transmission projects, said Nguyễn Tuấn Tùng, General Director of EVNNPT, a subsidiary of EVN.

Among the launched projects were the 500kV Long Thành substation, the 500kV Nho Quan Power substation, 220kV Ninh Phước substation, 220kV Tháp Chàm substation and 220kV Lao Bảo.

In 2019, EVNNPT also put into operation 43 projects, including 11 500-kV projects and 32 220-kV projects, ensuring power supply as required by the corporation and EVN.

According to EVN, this is an encouraging result as construction investment continues to face many difficulties, prolonged procedures for investment preparation and complicated site clearance compensation.

Last year, EVNNPT approved 63 feasibility studies, 42 technical designs; selecting contractors for 966 bidding packages of all kinds with the total winning bid value of about VNĐ14.5 trillion, and selected online contractors for 461 bidding packages. — VNS

 

 