Real estate projects in HCM City 's central area remain stalled

September 20, 2019 - 07:40
A number of real estate projects with investment of more than VND1 trillion in the centre of HCM City remain delayed even while the land area for new projects in the city has become increasingly limited.

 

 The inconsistencies between the Land Law and Planning Law have contributed to delays in the completion or start of major real estate projects in HCM City. — Photo baomoi.com

HCM CITY — A number of real estate projects with investment of more than VNĐ1 trillion (US$43 million) in the centre of HCM City remain delayed even while the land area for new projects in the city has become increasingly limited.

According to the city’s Department of Construction, contractors of these delayed projects are facing problems receiving permission to convert the land use to other purposes.

Lê Hoàng Châu, head of the HCM City Real Estate Association, said the inconsistency between the Land Law and the Planning Law, as well as other conflicts between laws, have also contributed to delays. 

Châu said the construction permit issuance and construction design evaluation process should be combined to shorten the time for granting construction permits.

Many real estate projects have been delayed since 2015. 

The Alpha Town project located at 289 Trần Hưng Đạo Street in District 1, a mall-service-office and apartment building, started construction in 2010. The project with total area of 4,000sq.m has been suspended since then.

The Lavenue Crown project at Lê Duẩn Street in District 1, a 4,900sq.m project, was slated to become a luxury hotel, but the vacant land plot, where a building that once stood on the plot was demolished, has been used as a parking lot for years. — VNS

 

 

  