Outstanding loans of twelve inefficient projects amount VNĐ21 trillion

May 22, 2020 - 07:42

The outstanding loans of twelve inefficient projects under the Ministry of Industry and Trade totalled nearly VNĐ21 trillion (US$905 million) as of the end of 2019, most were overdue, according to the Government’s report to the National Assembly.

 

DAP No 2 Lào Cai fertiliser plant, one among 12 inefficient projects under the Ministry of Industry and Trade which had been tackled since 2017. — Photo baodautu.vn

HÀ NỘI — The outstanding loans of twelve inefficient projects under the Ministry of Industry and Trade totalled nearly VNĐ21 trillion (US$905 million) as of the end of 2019, most were overdue, according to the Government’s report to the National Assembly.

The report said that the task of handling of these loss-making projects was around two thirds finished in the 2017-19 period but the remaining task was the most difficult, as problems were in settling disputes and finalising engineering, procurement and construction (EPC) contracts, debt restructuring and developing capital divestment plans.

There were some improvements since the handling effort was started in 2017 under Project 1468.

Two projects escaped losses and reported profits. DAP No 1 Hải Phòng fertiliser plant project reported an after-tax profit of VNĐ227.5 billion in 2018 and an estimated VNĐ6.2 billion in 2019. Việt – Trung steel plant earned an after-tax profit of VNĐ397 billion in 2018 and VNĐ177.4 billion in 2019.

The report said that these two projects saw lower profits in 2019 than 2018 because the market was more difficult.

Four projects saw their losses drop in 2018, including Hà Bắc nitrogenous fertiliser plant (down by VNĐ342 billion), DAP No 2 Lào Cai fertiliser plant (down by VNĐ208.8 billion) and Ninh Bình fertiliser plant (down by VNĐ417.2 billion).

The loss of Ninh Bình fertiliser plant continued to drop by VNĐ134 billion in 2019. However, Hà Bắc and DAP No 2 fertiliser plants saw bigger losses by VNĐ239 billion and VNĐ178.2 billion in 2019, respectively.

Dung Quất Shipyard Company’s losses also fell by VNĐ64 billion in 2019.

One project resumed operation, namely Đình Vũ Polyester Fiber Plant.

The report said that seven out of 12 projects remained loss-making, unfinished or halting operation.

Notably, five had disputes with partners of EPC contracts and settling disputes remained a big problem because a number of negotiations failed.

Those were DAP No 2 Lào Cai fertiliser plan, expansion project of Hà Bắc nitrogenous fertiliser plan, Ninh Bình fertiliser plan, Dung Quất shipbuilding plant project and second-phase expansion project of Thái Nguyên Iron and Steel Company.

Another big concern was the huge volume of outstanding loans of these projects, most were overdue.

Statistics showed that these projects owned debts worth VNĐ20.938 trillion as of December 31, 2019 to 17 commercial banks and one financial company, VNĐ17.169 trillion were medium and long term loans while VNĐ3.769 were short term.

Besides, Việt Nam Development Bank also provided outstanding loans worth VNĐ9.796 trillion to six out of 12 projects.

Banks also provided loans worth VNĐ22.964 to relevant contactors of these projects.

The report also said that a number of inspections were carried out to find out violations at these projects. Four were now under the investiation of the Ministry of Public Security.

The Government’s report also said that projects which could not be recovered would be allowed to go bankrupt or dissolved to maximise the recovery of the State capital and assets, ensure rights of workers and stabilise the business climate.—- VNS

 