Delayed dorms put students out in cold

HA NOI — Tens of thousands of students who will be travelling to Ha Noi for their first year at university next month are likely to be left searching for accommodation because the construction of two dormitory buildings has fallen behind schedule.

Figures from the municipal Department of Construction showed that construction of the two projects began in 2009 to provide accommodation for around 30,000 students.

Specifically, the My Dinh 2 dormitory, with a capacity of 7,400 students, and the Phap Van-Tu Hiep dormitory, with a capacity of more than 21,900 students, were among the key projects that needed to be completed by late 2011.

However, work on the two projects has yet to be completed due to a shortage of capital. The My Dinh 2 construction, with an area of 17,000 square metres and total capital of VND979 billion (US$46.9 million), has been delayed since early this year.

The Phap Van-Tu Hiep dormitory, with capital investment of VND1.4 trillion ($67.2 million) for six buildings covering 12,000 square metres, is in the same situation.

Chairman of the Hanoi Housing Development and Investment Corporation Nguyen Ngoc Tuan said the allocation of capital by the Ministry of Construction had failed to match the progress of the projects, causing serious delays.

Tuan said that the exteriors of the two projects had been completed, and once the interiors had been painted and fitted out, they would be put into use.

According to estimations from the department, the two projects needed about VND1.3 trillion ($62.4 million), including the debt capital the contractor spent in advance, to finish the last steps.

Head of the department's Housing Development Unit Vu Ngoc Dam said the city had approved funding of about VND300 billion ($.14.4 million) for the two projects, but affirmed this was not enough for their completion.

Dam said the city had asked the Government to allocate more than VND400 billion ($19.2 million) for the two projects.

Around 800,000 students from other provinces and cities live and study in Ha Noi. Despite a marked increase in the number of newly-established universities and colleges, authorities have paid little attention to building accommodation for students, with only 20 per cent currently housed in custom built dormitories. — VNS

Send Us Your Comments:
Name:
Your E-mail address:
Title:
 

VietNamNews may edit your comments and not all emails will be published.

Hightlight

Disabled speaker inspires audience Disabled speaker inspires audience

More than 2,500 people attended a talk by Nick Vujicic, an inspirational speaker without arms and legs, at the White Palace Conference Centre in HCM City's Tan Binh District yesterday.

Crane accident leads to major power cut Crane accident leads to major power cut

A two-hour power failure caused by an incident on the 500kV north-south transmission line hindered road traffic in many southern provinces and HCM City yesterday afternoon.

Spread of hand-foot-mouth disease concerns hospitals Spread of hand-foot-mouth disease concerns hospitals

Hand-Foot-Mouth disease (HFMD) is now at its peak, having infected a total of 796 children in HCM City in April, an increase of 127 per cent against the same period last year.

US steel producers make dumping claim US steel producers make dumping claim

After welded steel pipes and steel wire garment hangers, now welded stainless pressure pipe from Viet Nam continue to face charges of dumping in the US.