Vung Ang plant project speeds up

 

View of $1.4 billion Vung Ang 1 thermal power plant under construction. — VNA/VNS Photo Ha Thai
HA TINH — Construction of the US$1.4 billion Vung Ang 1 thermal power plant in the central province of Ha Tinh is in its final stage and will be completed by the end of this year, contractors said.

Head of project management Pham Van Dinh said about 98 per cent of equipment for the plant has been completed while 66 per cent of construction and installation is done.

He said contractors have installed the 7,500 tonnes boiler number 1, one of the most important tasks of the project, and also completed building the boiler house.

"Despite severe climates, overall construction is 80 per cent finished," he added.

With investment from the Viet Nam National Oil and Gas Group (PetroVietnam), the project is part of the National Power Development Plan for 2006-15. It will be the first coal-fuelled power plant to be built in the northern central region.

Nguyen Duy Loi, deputy head of LILAMA's project management board, the project's main contractor, said as many as 100,000 tonnes of equipment have been installed and of which 46,000 tonnes were produced locally.

"We have increased the number of workers in the construction field from 2,500 to 3,500 to accelerate the speed of construction."

Loi said the Viet Nam Machinery Installation Corporation (LILAMA) has mobilised most of its strongest affiliates such as the LILAMA 18, LILAMA 69-1.

Once fully operational by the first quarter of 2013, the 1,200 MW plant will supply nearly 7.2 billion kWh a year to the national grid.

The government last year approved the plan on national power development for 2011-20, which is also called master plan 7.

According to the plant, Viet Nam strives to have a power generation capacity of 75,000 MW by 2020 and 146,800 MW by 2030.

Hydropower plants would generate 23.1 per cent of the total capacity, pumped storage hydroelectric plants 2.4 per cent, thermopower coal-run plants 48 per cent and gas-run thermopower plants 16.5 per cent.

The country also plans to draw 5.6 per cent of the total capacity from renewable energy, 1.3 per cent from nuke plants and 3.1 per cent from imports.

The total investment capital of the power industry would be $48.8 billion by 2020.-VNS

Send Us Your Comments:
Name:
Your E-mail address:
Title:
 

VietNamNews may edit your comments and not all emails will be published.

Highlight

PM meets acclaimed local mathematician PM meets acclaimed local mathematician

Prime Minister Nguyen Tan Dung yesterday met Professor Ngo Bao Chau, the first Vietnamese to win the Fields Medal, the highest professional honour a mathematician can attain, and the Education Dialogue Group.

Scholars discuss East Sea dispute at int'l conference Scholars discuss East Sea dispute at int'l conference

The East Sea dispute will continue in the near future and urgent solutions should be found to manage the conflict and resolve it without force or the threat to use force and protect the rights of fishermen in traditional fishing grounds, an international conference that opened in HCM City yesterday agreed.

Police look into scam claims at pagoda Police look into scam claims at pagoda

Police are investigating rumors that a pagoda in Long Bien District is selling children for adoption.

A Vietnamese and a Chinese arrested for ivory smuggling A Vietnamese and a Chinese arrested for ivory smuggling

Customs officials have arrested a Chinese woman and a Vietnamese man at Suvarnabhumi Airport after they allegedly tried to smuggle out elephant tusks and ivory products worth about BAT9 million.

Places for a vacation: Son Doong Cave Places for a vacation: Son Doong Cave

Son Doong Cave in Viet Nam's Quang Binh Province has been suggested by the American news website huffingtonpost.com as one of the places to visit in 20 years.